Bend parks board drops river trail route near Sunrise Village
The neighborhood's HOA pushed back, and staff say two other stretches stay in play.
BEND, Ore. - The Bend Park and Recreation District board backed a staff recommendation Tuesday night to drop one of the toughest stretches of the long-planned Deschutes River Trail South extension, the gorge route near Sunrise Village, the district said in a meeting summary.
No vote was needed. The agenda item was an update only, with no action proposed, according to the board packet. But the summary says board members voiced support for the recommendation and thanked staff for the extra homework. You can watch the whole meeting in the district's video.
Why Section 2 fell away
Directors had asked staff on Oct. 6 to take a second look at Section 2 of the study area, to see whether a workable bridge and trail location existed outside the State Scenic Waterway. Principal Planner Henry Stroud and consultant Matt Kittelson reviewed two possible routes.
They found steep canyon terrain, complex and costly construction, nearby irrigation facilities, effects on the scenic waterway and heavy private-property impacts. One route would use an existing private staircase and connections through Sunrise Village. A more direct riverfront route would cross the HOA's property and seven other private properties.
Scott Hand, vice president of the Sunrise Village HOA board, spoke during visitor comments for the board and neighbors. He said the HOA is not against trails but does not support an alignment through its private property, and he urged the district to find connections that avoid protected areas and private land.
Staff also said neither Section 2 nor Section 3 would fully close the gap in the existing river trail. Section 1 offers a more direct chance to do that.
What happens next
The study moves into its alternatives phase, with a closer look at costs, travel distances and private-property effects, plus talks with the project's stakeholder group. Staff expect to bring the board two preferred alternatives in spring 2027.
The district's project page lists $300,000 in system development charge funds for the study, with an estimated finish of April 2027. The packet says the district hired Kittelson & Associates for $270,284, including contingency, and the study will include rough cost estimates for the two preferred alternatives. The project page describes the work as a bid to fill one of the last gaps on the river trail between Sunriver and Tumalo State Park.
Also on the agenda
Optimize Play. Staff said 199 employees have finished training and have found 49 ways to work better across seven departments. Of those, 34 are done and 15 are underway. Standardized custodial purchasing is expected to save about $12,000 to $20,000 a year.
Rentals and events. Requests for park use keep outrunning space. Staff said 76 requests were denied in 2024 and 127 in 2025, with Drake, Riverbend, Shevlin and Pine Nursery parks feeling the most wear. The board generally supported staff's approach of steering events to other parks while keeping room for unplanned use.
Legislature. The board supported writing to the district's legislators about keeping system development charge funding for parks, trails and recreation.
The board meets next Dec. 1.
Source: Bend Park and Recreation District, Summary of Nov. 17 Board of Directors meeting; meeting video.