De Soto USD 232 bond projects scheduled through 2029, starting with two additions
Monticello Trails and Cedar Trails additions are under construction; middle, high school and elementary work follows in 2027 to 2029.
DE SOTO - De Soto USD 232 has begun the first construction funded by its 2026 bond and plans to keep building through summer 2029, according to the district's Bond 2026 page and Board of Education records.
Voters approved up to $99.85 million in bonds on March 3, 4,089 to 2,458, official Johnson County results show. The board sold the first $70 million in June.
Work began this fall on additions at Monticello Trails Middle School, for special education, orchestra and a multipurpose room that doubles as a storm shelter, and on early childhood classrooms at Cedar Trails Exploration Center. On Sept. 14 the board approved a $16.6 million guaranteed maximum price, 6-1, with substantial completion set for Aug. 6, 2027.
Elementary security fencing, up to $403,402, is due this winter, and key-card door access, $283,738 plus contingency, in August 2027.
On Nov. 2 the board considered a $2.54 million turf and track rebuild and $333,000 in lighting at Mill Creek Middle School, targeted for fall 2027. Minutes of that meeting are not yet posted.
Later phases
- Mill Creek Middle and CTEC CAPS additions: opening fall 2028.
- Mill Valley High renovations and bridge improvements: opening fall 2028.
- Lexington Trails Middle additions, De Soto High addition and renovation: opening winter or spring 2029.
- Elementary classroom addition: summer 2029, on a January draft schedule.
Source: USD 232 Bond 2026; Johnson County election results; April bond timeline; Draft project schedule; Phase 1 GMP memo; Sept. 14 minutes; July 13 minutes; June 1 minutes; Mill Creek track memo; Mill Creek lighting memo; Oct. 5 bond update.
- De Soto USD 232, Bond 2026 page
- Johnson County Election Office, official final results, USD 232 question, March 3, 2026
- USD 232 Board of Education, April 6, 2026, Bond 2026 update presentation (phase timeline)
- USD 232, Draft Project Schedule and Concept Plans, Jan. 12, 2026 board packet
- USD 232, 2026 Bond Phase 1 GMP memo and Newkirk Novak bid summary, Sept. 14, 2026
- USD 232 Board of Education minutes, Sept. 14, 2026
- USD 232 Board of Education minutes, July 13, 2026
- USD 232 Board of Education minutes, June 1, 2026
- USD 232 Bond Resolution, GO Bonds Series 2026-A
- USD 232 memo, Mill Creek Middle School track and field renovation, Nov. 2, 2026 agenda
- USD 232 memo, Mill Creek Middle School track and field lighting, Nov. 2, 2026 agenda
- USD 232 Bond 2026 update presentation, Oct. 5, 2026
- USD 232 Board of Education meetings portal (Nov. 2, 2026 agenda)