$308.6M plan to pipe Logan, North Logan and Hyde Park irrigation awaits federal decision
The federal share would be $275.9 million. A May federal timeline listed first-phase construction in fall 2028, pending approval and funding.
LOGAN - A plan to move irrigation water in Logan, North Logan and Hyde Park out of open canals and into a pressurized pipe system, and to add flood protection, would cost an estimated $308,633,000, according to a federal draft environmental impact statement (link). Federal watershed funds would pay $275,893,400 and local sponsors $32,739,600.
Cache Water District is the sponsor. The preferred plan would add at least 25 cubic feet per second to summer flows for 14 miles of the Logan River, store 2,100 acre-feet in old sewage lagoons and reduce flood impacts for 28 homes near the river, a federal fact sheet (link) says.
Public comment closed June 22. A May federal presentation (link) listed first-phase construction in fall 2028, pending approval and funding. The district's manager, Nathan Daugs, told The Utah Statesman (link) he hopes for a federal decision shortly after the new year, with funding still to be found.
A 2024 Logan fact sheet (link) estimated secondary water at $30 to $70 a month, depending on how many users connect and before any city contribution.
Why this matters
Construction, and any change in residents' water costs, depends on federal approval and money.
Source: Natural Resources Conservation Service project page (link), Draft Plan-EIS (link) and fact sheet (link).
- USDA NRCS, Logan River Watershed Project page (page updated May 20, 2026)
- USDA NRCS, Draft Logan River Watershed Plan-EIS (May 2026; 305 pp.)
- USDA NRCS, Logan River Project Overview Fact Sheet (September 2024)
- USDA NRCS, Logan River Public Comment Meeting presentation, May 20, 2026
- USDA NRCS, Logan City fact sheet (September 2024)
- Cache Water District, Watershed Studies page