Government  /  American Fork City Council meeting, Nov. 10

Council packet included change order request adding about $312,000 to Dixie Well drilling contract

Engineering requested additional construction funds for Dixie Well drilling after unforeseeable subsurface conditions required switching to cable‑tool drilling and advancing 28" casing; the packet lists an additional $312,134.25 (and also includes a later page showing $315,176.00) and says the work is funded by Culinary Water Impact Fees.

ShareFacebookXEmail

Engineering staff asked the council to approve additional funds for the Dixie Well Drilling Project contract with Hydro Resources - Rocky Mountain, Inc., citing unforeseen subsurface conditions that created a void in unstable gravely soil. The packet explains continuing with the rotary rig would be unsafe; Hydro Resources proposed removing the rotary rig, using a cable‑tool rig to extend 28" casing to approximately 185 feet, then returning the rotary rig to drill to design depth. The change in method also required moving the rig off site and engaging subcontractors.

The packet lists the original contract total as $2,327,733.00 with an approved contingency of $200,000.00. A project change order form in the packet states "AMOUNT OF THIS CHANGE ORDER $312,134.25" and shows a new contract price of $2,639,867.25 and a 56‑day extension to a substantial completion date of Feb. 1, 2027. Multiple line‑item exhibits break the cost into items such as cable‑tool drilling advance of 28" casing ($160,600.00), 28" casing materials and freight, rig moves, and a 15% markup on certain third‑party costs.

The packet also contains alternate line‑item summaries on later pages that display a slightly different net contract adjustment figure of $315,176.00 and a new contract sum of $2,642,909.00. The packet does not explain the discrepancy between the two net adjustment figures; both appear in documents submitted for council consideration. The cover materials state the project is funded by Culinary Water Impact Fees.

The suggested motion reads: "Mr. Mayor, I move that the City approve an additional $312,134.25 in project construction for the Dixie Well Drilling Project under construction and being performed by Hydro Resources - Rocky Mountain, Inc." The item was scheduled for the council's Nov. 10, 2026 meeting at 7:00 p.m.

Written by Citizen Portal from public meeting records and published automatically. No local editor reviewed it.