Council asked to approve ~ $312,000 drilling change order and schedule extension for Dixie Well

Engineering asks the Council to approve Change Order No. 1 with Hydro Resources for the Dixie Well drilling project to address unstable subsurface conditions, requesting an additional $312,134.25 and a 56‑day contract time extension with a new substantial completion date of Feb. 1, 2027; the work is funded by Culinary Water Impact Fees.

ShareFacebookXEmail

An Engineering staff report asks the City Council to approve additional funds for the Dixie Well drilling contract to Hydro Resources - Rocky Mountain, Inc. due to unforeseeable subsurface conditions.

The packet states the original drilling contract with Hydro Resources was $2,327,733.00 with an approved contingency of $200,000.00. Unstable, gravely soils and a void encountered at depth require changing the drilling method: Hydro Resources will remove the rotary rig, a subcontractor will advance a 28" intermediate casing using cable‑tool drilling to stabilize the hole to approximately 185 feet, Hydro Resources will then resume rotary drilling to the design depth. The packet says this change will require moving rigs on and offsite and other third‑party work.

Staff’s budget impact section requests an additional $312,134.25 for Change Order No. 1, which the packet says would result in a new contract total of $2,639,867.25 and extends substantial completion by 56 days to Feb. 1, 2027. The packet explicitly states the project is funded by Culinary Water Impact Fees. Change‑order exhibits attached to the packet list detailed line‑item pricing for cable‑tool drilling, 28" casing, trucking, sound‑wall reinstallation and a 15% markup on third‑party costs. One attachment shows alternate line‑item math and an alternate net CO amount appearing as $315,176.00 and a new contract sum of $2,642,909.00; the packet includes both sets of line‑item exhibits.

The staff suggested motion reads: “Mr. Mayor, I move that the City approve an additional $312,134.25 in project construction for the Dixie Well Drilling Project under construction and being performed by Hydro Resources - Rocky Mountain, Inc.” The Council is scheduled to consider the request at its Nov. 10, 2026 regular session at 7:00 p.m. at American Fork City Hall, 31 North Church Street.

Written by Citizen Portal from public meeting records and published automatically. No local editor reviewed it.